City of Las Cruces Streets Management began applying today, Wednesday, Sept. 18, 2019, a chip seal surface treatment on various streets. The work is scheduled to be completed Thursday, Sept. 19, 2019. However, this schedule is subject to change.
Streets to be affected include:
- West Ethel Avenue, from north Alameda Boulevard to north Miranda Street.
- Houma Street, from Palmer Road to west Ethel Avenue.
For the public’s convenience, crews will work from 6 a.m. to 6 p.m., Monday through Friday, leaving the weekends free of construction activity. Access to residences and businesses will be maintained with periodic closures during the construction period. Motorist are asked to find alternate routes. The closure will not affect RoadRUNNER Transit routes.
The City has verified that no conflicting public or private construction projects will take place in that immediate area during this time.
For information, call Street Management at 575/541-2595.