Marquess Street (Boutz Road to South Valley Drive) is scheduled to be repaved and have ADA improvements done by Highland Enterprises, Inc. as part of a City pavement replacement project. The project will begin Monday, May 6, and is estimated to conclude on Friday, May 24. Work will take place between 7 a.m. and as late as 6 p.m. During construction, the roadway will be accessible to Marquess Street residents/businesses. The work will also require intermittent right lane closures on both South Valley Drive and Boutz Road.
The City has verified that no conflicting public or private construction projects will take place in that immediate area during this time and RoadRUNNER Transit routes will not be affected.
On-street parking on these roadways will not be possible during construction.
For more information, contact the Public Works Department, Construction Management at 575/528-3098. The TTY number is 575/541-2182.